RO4360 material identification

Resolve the precise grade and current document before assigning numeric design properties. Use the explanations, source documents and interactive calculations to make the next engineering decision with clear assumptions.

Bring your band, stackup, quantity and acceptance requirements. Preliminary files are welcome for review.

RO4360 board example
RO4360 board example as identified in the original 勛圖tv media catalogue. Photograph only; material identity and acceptance for an order require its build records.

Start with the engineering decision

Legacy RO4360 is not automatically RO4360G2

A G2 suffix identifies a distinct documented product. A legacy RO4360 drawing should be checked against its original material record before using current G2 data. If migration is intended, make it a visible design change with the relevant electrical, mechanical and procurement review. The calculator does not supply an unverified legacy Dk.

RO4360 material identification decision framework
Planning itemWorking definition
Primary taskResolve the precise grade and current document before assigning numeric design properties
Model boundaryIdentify the construction, units, method and acceptance question before calculation.
Useful outputA documented decision, a reproducible model or a complete fabrication brief.
Next engineering stepRogers PCB distributor: Specification & Quotation

A verified single design Dk has not been assigned to this construction. The tool leaves uncertain material fields open. Obtain the original designation and applicable supplier document before adopting numeric properties.

Material identity brief

Use explicit construction inputs. Results can be downloaded or opened as an email draft; the tool does not upload project information.

Worked planning example

A complete identity record might contain a grade and suffix, a dated supplier document, the selected thickness and foil, and a statement that any substitution needs approval. Unknown Dk and loss values should remain open until that construction is identified. A blank field is more useful than an unsupported default.

Use the result to inspect scale and sensitivity. Preserve the input units and assumptions in the downloaded brief, then use the actual finished geometry and appropriate solver or measurement method for release.

勛圖tv ENGINEERING

Rogers Engineering Workbench

Rogers Engineering
Loading Rogers Engineering Workbench…
Using this tool & sharing results

Use the stated units, input limits and model assumptions. Results support an engineering discussion; they do not approve a design, process or production order.

After changing inputs, update the result before using it. Where a download or copy action is available, review that brief and attach or paste it into your enquiry. Opening Contact does not transfer these inputs or send a request.

How to use and share tool results

The engineering record connects material identity, stackup, geometry, process and verification.
The engineering record connects material identity, stackup, geometry, process and verification. Original engineering illustration.

Recovering a legacy material without inventing a replacement

Older circuit drawings often preserve a trade name after the product range, documentation or supply route has changed. The correct first step is to identify the exact material that the design used. Record the complete designation, suffix, datasheet date, thickness and foil construction. A current web page with a similar name is not enough to establish equivalence. Neither is a product photograph, because visually similar RF boards can use very different dielectric systems.

Separate three questions: what was originally specified, what can be sourced now, and what a replacement would need to demonstrate. An archived document can answer the first question while saying little about present availability. A supplier quotation can answer availability for a particular construction, but it does not automatically qualify the material for an old design. Engineering acceptance needs a comparison of the relevant properties and the finished circuit behavior.

For an RF replacement, compare more than nominal dielectric constant. Include the appropriate design model, loss behavior over the operating band, thickness tolerance, copper profile, temperature dependence and mechanical construction. Review bond compatibility, machining and assembly exposure as well. If the old model is unavailable, plan how to correlate a representative coupon or prototype rather than selecting a new value merely because it produces a familiar trace width.

Maintain a clear distinction between a safety information sheet, an electrical datasheet and a fabrication guide. The safety sheet helps identify handling considerations and the product name; it is not a complete electrical design specification. An old test report may describe one material lot or sample configuration. Preserve the date and test context when using that record, especially if the new build changes thickness, foil or processing.

The material-identification tool creates a structured request without filling unknown engineering inputs with plausible numbers. Send the original drawing and any retained laminate records with the enquiry. Mark substitutions as requiring approval until the design authority has reviewed them. A controlled qualification build can then resolve the open questions in a visible sequence: identity, construction, geometry, fabrication, measurement and release.

勛圖tv rogers 6002 pcb construction example
Related ROGERS 6002 board photograph from the 勛圖tv media catalogue. Used to explain construction; not evidence that the pictured board uses the material discussed on this page.
Process, design and effective dielectric values describe different measurements or models.
Process, design and effective dielectric values describe different measurements or models. Original engineering illustration.

Define the board that should be quoted and manufactured

An RF board quotation is most useful when it describes the same construction that the design team intends to release. State the exact laminate grade, dielectric thickness, copper and finished board thickness separately. Add the layer sequence, outline and drill information. For a multilayer, name the bonding products rather than listing only the outer RF core. If a choice is still open, identify it as an engineering question in the request.

Mark the RF dimensions that deserve particular attention. Examples include a narrow coupling gap, a connector launch, a resonator edge or a line routed over a specific reference plane. A controlled-impedance requirement should identify the signal layer, reference layer, target and tolerance. It should also state the coupon or measurement expectations when those are part of acceptance. A generic statement that all traces are fifty ohms is rarely enough to resolve a complex circuit.

Keep finished copper and base foil distinct. Plating and etching can change the conductor cross-section used in the electrical model. Surface finish, solder mask and nearby cover materials can also affect exposed RF structures. Ask the fabrication review to return any proposed change to these assumptions before the design is frozen. An unexplained substitution can make an apparently cheaper quotation difficult to compare with the intended build.

The first build should test the assumptions that matter to the product. A continuity result verifies connectivity. An impedance coupon provides evidence for its represented line structure. RF insertion-loss, phase or filter-response testing requires additional fixtures, reference planes and acceptance conditions. Agree the scope before ordering so that the delivered records answer the intended engineering question.

For assembly, add the bill of materials, placement data, assembly drawing and test plan. Include special connector, heat-spreader or device-attachment requirements early. The fabrication and assembly scopes can then be reviewed together while remaining separately identifiable in the quotation. The direct enquiry route on this page is available without completing the calculators; the tools simply help make the technical brief clearer.

Cost planning and a direct RFQ route

Where the cost changes, and which savings are real

For a small RF order, setup, procurement and test preparation may matter as much as the area of laminate. A panel that holds more circuits spreads some shared effort across more boards, but only if the orientation, tooling and coupon requirements permit that layout. The budget tool uses an explicit rectangular nesting model so that its area assumption can be inspected. It does not assume every visible square millimeter of a panel becomes a delivered board.

Copper foil, core thickness and bonding system are part of the purchased construction. A quotation based on a different thickness or foil is not a clean price comparison, even when the headline material name matches. Ask whether the offered material is standard for the supplier's available construction and whether minimum purchases, special handling or qualification work affect the lot. Availability and lead time must be confirmed for the actual order rather than inferred from a web page.

Complexity can move cost in several directions. A hybrid stack may reduce the amount of premium RF laminate while adding press planning and interface review. Metal backing can improve a thermal path while adding bonding and machining requirements. Extra coupons or RF fixtures can reduce uncertainty but add material, setup and measurement work. Compare the complete project scope instead of ranking designs by laminate price alone.

The optional numerical budget uses cost allowances entered by the visitor. It contains no calibrated 勛圖tv tariff and does not claim current market pricing. The model combines the costed panels, one-time setup, batch testing and per-board processing; assembly is included only when selected and entered. Shipping, taxes, process yield loss and unentered qualification are excluded. A zero value means already included or deliberately zero, not unknown.

When geometry, quantity or supply scope changes, revisit the allowances. A per-board processing cost from one batch may not apply to another. The tool clears old allowances on those changes to avoid presenting a stale total. Hybrid, metal-backed, unresolved and more complex multilayer constructions go to engineering quotation. The downloaded brief remains useful because it carries the requirements and assumptions even when a numerical price would be misleading.

勛圖tv ENGINEERING

Rogers Fabrication Budget & RFQ

Rogers Engineering
Loading Rogers Fabrication Budget & RFQ…
Using this tool & sharing results

Budget outputs are planning scenarios. Check the included costs and rate assumptions; a confirmed quotation requires a review of your files and scope.

After changing inputs, update the result before using it. Where a download or copy action is available, review that brief and attach or paste it into your enquiry. Opening Contact does not transfer these inputs or send a request.

How to use and share tool results

Prefer to send files now? Contact the 勛圖tv team with the requested material, construction and quantity. An exact quotation is based on the agreed scope.

Verify the construction that matters to the product

A measurement plan that answers the design question

Begin with what the prototype must establish. Is the question electrical continuity, line impedance, insertion loss, phase balance, resonant frequency, thermal behavior or mechanical fit? These are different tests and they may require different coupons, fixtures and acceptance limits. A test label without the represented structure and measurement method leaves room for two parties to interpret the result differently.

For RF measurements, define the reference planes and account for the launch or fixture. A raw network-analyzer trace can include connectors and transitions that are not part of the material comparison. De-embedding or a representative reference structure may be needed, depending on the question. Record calibration, frequency span, temperature and the circuit revision with the result. This makes later comparisons more informative than a single unqualified pass statement.

Investigate a disagreement between the model and the board in a controlled sequence. Check the finished conductor dimensions, dielectric height, material construction and measurement setup before changing the Dk to force a fit. The model may omit a nearby cover, a return-path discontinuity or a loss mechanism. Equally, the test fixture may represent a different structure from the intended coupon. Identifying the cause protects the next build from an accidental compensation.

Keep the accepted construction and records together. A successful prototype supports the tested revision under its stated conditions. Changes to material, foil, bond system, geometry, assembly exposure or test scope deserve review before a repeat order is treated as equivalent. The project does not need every possible test; it needs the evidence that resolves its actual risks and acceptance requirements.

勛圖tv rogers 4003c pcb construction example
Related ROGERS 4003C board photograph from the 勛圖tv media catalogue. Used to explain construction; not evidence that the pictured board uses the material discussed on this page.
Define reference planes and representative geometry before comparing model and measurement.
Define reference planes and representative geometry before comparing model and measurement. Original engineering illustration.
勛圖tv ENGINEERING

Rogers Construction Explorer

Rogers Engineering
Loading Rogers Construction Explorer…
Using this tool & sharing results

Use the stated units, input limits and model assumptions. Results support an engineering discussion; they do not approve a design, process or production order.

After changing inputs, update the result before using it. Where a download or copy action is available, review that brief and attach or paste it into your enquiry. Opening Contact does not transfer these inputs or send a request.

How to use and share tool results

Questions before the next design or purchase decision

What should this page help me decide?

Resolve the precise grade and current document before assigning numeric design properties. Start with the named construction and the relevant engineering requirement. The photographs show physical circuit examples, while the original-source links and explicit model assumptions support the technical review.

What is the most important construction detail here?

RO4360 versus G2 identity. Keep that decision in the released drawing and ask the supplier to identify the offered construction explicitly. For this material, the follow-up verification should address controlled migration to a current construction.

Does the design tool approve this PCB for manufacture?

No. It calculates the stated preliminary model or organizes a construction brief. Finished copper, transitions, mixed dielectrics, assembly interfaces and process limits may require a more complete review. The downloaded result preserves assumptions so engineering can evaluate the same inputs.

Can I obtain a price without completing the tool?

Yes. Use the direct Contact or email route with your drawing, quantity and construction requirements. The optional budget uses your entered allowances and an explicit panel model; it is not a calibrated 勛圖tv tariff. Complex constructions need a file-based quotation.

What should I send with an enquiry?

Include the exact material designation, fabrication artwork, drill data, outline, proposed stackup, copper, finish and quantity. Add the relevant impedance, RF, thermal or mechanical acceptance requirements. If assembly is included, provide the BOM, placement data and test expectations.

Continue with the right engineering task

Original technical references

Supplier documents support material identity, properties and methods. They do not establish current stock or qualify an unspecified finished board. Check the exact grade, construction and document revision for your order.